Implementation Period |
Activity |
|
October 2005 |
IFMIS
Supplier Contracted
|
|
November 2005
– June 2006 |
Procurement
of the IFMIS software, consultancy, training and
IT/communications hardware
|
|
February 2006 |
Implementation of IFMIS activities commenced by the Supplier
|
|
February 2006 – July 2007 |
Pilot
implementation of Phase I of the IFMIS, which will cover 6
Pilot sites
|
|
2nd January 2007 |
IFMIS Go-live
date for Phase 1
|
|
January 2007 – July 2007 |
Parallel run,
testing and operational acceptance activities
|
|
July 2007 – December 2007 |
Periodic
financial reports, Budget module post-implementation
processes and Phase 1 closure activities
|
|
January 2008 – December 2008 |
Implementation of Phase 11 of the IFMIS, which will cover 17
Departments of State.
|
|
January 2009 |
End of year
financial reports, Budget post-implementation processes and
Phase 11 closure activities
|
|
February 2009 – June 2009 |
Implementation of Phase 111.A. of the IFMIS which will cover
interfaces with the Debt Management, ASYCUDA, Personnel
Management, Tax Administration and Central Bank systems
|
|
February 2009
– December 2009 |
Implementation of Phase 111.B. of the IFMIS which will cover
additional modules at the Directorate of National Treasury
|
|
January 2010 |
Project
completed
|